Proactive and Reactive Constraint Programming for Stochastic Project Scheduling with Maximal Time-Lags
Abstract
This study investigates scheduling strategies for the stochastic resource-constrained project scheduling problem with maximal time lags (SRCPSP/max). Recent advances in Constraint Programming (CP) and Temporal Networks have re-invoked interest in evaluating the advantages and drawbacks of various proactive and reactive scheduling methods. First, we present a new, CP-based fully proactive method. Second, we show how a reactive approach can be constructed using an online rescheduling procedure. A third contribution is based on partial order schedules and uses Simple Temporal Networks with Uncertainty (STNUs). Our statistical analysis shows that the STNU-based algorithm performs best in terms of solution quality, while also showing good relative offline and online computation time
Authors
Keywords
No keywords are indexed for this paper.
Context
- Venue
- AAAI Conference on Artificial Intelligence
- Archive span
- 1980-2026
- Indexed papers
- 28718
- Paper id
- 92353604497418570